- MACT stack test protocol letter for kiln K1 - 02/22/06. (S.Vogel)
- Notification of operation of kiln K1 with DLA - 02/15/06. (B.Kennedy)
- DAQ issues T06 for DLA installed on kiln K1 - 11/28/05. (G.Patnaik)
- Application received for kiln K1 with DLA - 10/14/05. (G.Patnaik)
- DAQ issues Notice of Violation for late report - 08/11/05. (B.Kennedy)
- DAQ receives stack test report from Triangle Brick - 04/29/05. (M.Revels)
- EPA reconsidering DLA technology for MACT - 04/22/05. (FR)
- DAQ inspection and brick kiln MACT stack test - 03/24/05. (B.Kennedy)
- T05 issued for 2nd brick kiln with DLA - 09/22/04. (J.Twisdale)
- Construction request for 2nd brick kiln is approved - Feb. 2004. (K.Godwin)